This project consists of the removal and replacement of a 10' asphalt trail from Grand Street to north of 187th Terrace.
Project Status/Tentative Schedule
Week of Oct. 14 - Complete restoration work
Week of May 28, 2024: Construction begins
April 2024: Project expected to be awarded to contractors
Traffic Impacts
Motorists can expect intermittent lane closures. Flaggers will be on-site to help direct traffic.
Comments, Questions and Requests
Please contact the Public Works Department for any questions or comments at 913.856.0914 or engineering@gardnerkansas.gov. Click here to submit a service request.